LONDON — The House of Commons Transport Committee said on November 26 that the UK government’s draft policy does not make a convincing case for a third runway at London Heathrow Airport (LHR). Its report on the draft Heathrow Expansion National Policy Statement calls for a fuller economic assessment and clearer plans to pay for rail improvements. The committee also concluded that expansion would not be compatible with the UK’s legally binding climate targets under current policies.
The review concerns the rules that would guide a future planning decision, not whether to grant Heathrow permission to build. Ministers selected Heathrow Airport Limited’s northwest runway scheme as the basis for the policy review in November 2025. Airways previously covered Heathrow’s proposal for the runway and new terminal capacity.
Modeling commissioned by the Department for Transport found that annual real GDP could be up to 0.05% higher in 2056 than in the baseline without expansion. The department’s revised assessment of broader costs and benefits put the net present value between minus £53bn and minus £14bn. In that analysis, wider societal and environmental costs outweighed gains such as lower fares and fewer delays. The committee said ministers should bring the two strands of analysis together and provide Parliament with peer-reviewed results before finalizing the policy.
The committee also asked ministers to drop the proposed designation of Heathrow expansion as Critical National Growth Infrastructure or provide stronger evidence for it. It recommended publishing a wider aviation strategy before any parliamentary vote on the policy, so lawmakers can judge what Heathrow adds alongside other UK airports.
Lawmakers warned that if charges to use Heathrow rise too far, airlines could be less willing to use the new capacity. They asked the Civil Aviation Authority to consult on an upper level for landing charges, beyond which the benefits of expansion could be undermined, and to clarify which costs the developer would have to cover by other means.
The committee also said there is no firm, funded rail plan for an expanded Heathrow. It wants the final policy to identify which rail schemes the government supports and require an independently checked funding plan for ground transport before granting development consent. The plan would have to show who pays for rail improvements and substantiate the government’s claim that taxpayers would not bear the cost.
The Department for Transport says it will weigh consultation responses alongside the committee’s recommendations. Heathrow started its own consultation on a proposed development consent application on October 27. That is a separate process, and a promoter must still apply for permission to build.
Featured photo: APK/Wikimedia Commons, CC BY 4.0.